Hello everyone from #HIVE and members of SWC, I'm Milano Alfinger @ashura-sw, today I want to share with you about the bar notice that together with my training partners we managed to set up in my house 🏠 which is named "BARRbara" 😁 it was a process of several days but in the end we achieved what we proposed with recycled materials, if you want to know more about the process and why he was baptized with that name 😂 keep going down to find out everything.
Well, the project began on December 10, 2022, we already had all the materials to start the construction of the high bar, but first we had to clean the area that was quite in poor condition due to the growth of the plants, as can be seen In the photo above we had already managed to uproot the plants and we only had to wait for them to dry before we could get rid of them, that same day we began to open the holes in the ground to calculate how deep we would put the base of the high bar.
Después de haber esperado 3 dias para que se secarán las plantas y que mi tío viniera a mi casa para apoyarme en el proyecto comenzamos con la construcción, primero con el esmeril cortamos los tubos que íbamos a utilizar para poder soldarlos a la base.
After having waited 3 days for the plants to dry out and for my uncle to come to my house to support me in the project, we began the construction, first with the emery we cut the tubes that we were going to use to be able to weld them to the base.
Una ves soldados los tubos a la base después de haber cuadrado bien la distancia entre cada una de ellas (2 metros de distancia entre las bases), procedimos a introducir la barra fija en el suelo depende estaban los huecos, ya cuadrando perfectamente la alineación de la barra comenzamos a preparar la mezcla de cemento 🧱 para hecharlo en los hoyos.
Once the tubes have been welded to the base, after having squared the distance between each one of them (2 meters of distance between the bases), we proceeded to introduce the fixed bar into the ground depending on where the holes were, and perfectly squaring the alignment of the bar we begin to prepare the cement mix 🧱 to put it in the holes.
Ya faltando poco para culminar la barra fija aún faltaba colocar los soportes frontales de la barra, con unas bases recicladas se hicieron esos soportes, lo cortamos y soldamos a la base de la barra.
Finalmente llegamos a la parte final, pintar la barra, con una pintura en aerosol negra se pinto la base y con el anticorrosivo de fondo a la barra dándole un acabado negro con gris a la barra fija, ya una ves terminado de pintar esperamos a que se secaran la pintura todo el fin de semana y finalmente logramos estrenar nuestra preciosa "BARRbara" y aunque llevamos poco tiempo de usarla hasta sol de hoy seguimos muy contentos de haber podido lograr contruir lo que pensamos era imposible para nosotros que no contábamos con los recursos necesarios para hacerlo y gracias al apoyo de mi tío que nos ayudó con su experiencia y en la soldadura lo logramos.
Llegados a este punto solo queda decir por fin teníamos nuestra barra fija, ahora el porque fue bautizado como "BARRbara", pues simplemente yo quería ponerle un nombre pero no sé me ocurría nada hasta que uno de los muchachos con los que estaba dijo que BARRbara sería buena idea y no me tomo ni medio segundo para decir, ¡¡¡sí!!! Ese será su nombre, y bueno nada así se quedó 🤣🤣
|
---|